Wind Turbines

An Coimisiún Pleanála Annual Report 2025

Renewable Energy and Private Strategic Infrastructure – Analysis of 2025 Annual Report. The Commission published its 2025 Annual Report on 20th October 2026.

An Coimisiún Pleanála made clear progress in overall case management during 2025, but the improvement has not yet translated into materially faster processing of renewable energy and other Strategic Infrastructure Development (SID) projects.

2025 performance at a glance

Indicator20242025Change/reading
SID cases received142177+24.6%
SID cases decided175139-20.6%
Average SID processing time53 weeks54 weeksNo material improvement

What the data says

Private SID: Direct SID applications increased from 45 to 59 (+31%), but decisions fell from 70 to 57. Excluding RED III cases, 128 private/statutory-undertaker SID cases remained on hand at year-end.

Renewable energy/RED III: The revised EU Renewable Energy Directive (Directive (EU) 2023/2413), known as RED III, became operational on 7th August 2025. The renewable caseload increased from 19 cases at the start of 2025 to 39 at year-end: only 9 were concluded during 2025.

Offshore: Five Phase One offshore renewable energy applications remained under assessment at year-end, all having received further information requests.

Renewable energy judicial review outcomes in 2025

12 wins, 6 withdrawals, 1 no-fault disposal, 3 concessions and 3 losses

Of the 25 judicial reviews concluded in 2025, 12 were won, 6 were withdrawn and 3 were conceded, with 1 no-fault disposal and 3 losses.

What it means for renewable energy projects

Positive: Overall case backlog was falling, statutory compliance with respect to appeals improved in 2025, digital case management was strengthened and additional staffing was approved.

Continuing challenge: Strategic infrastructure remained slow to process, with average determination time around one year and no improvement in SID statutory compliance.

Key industry message: The 2025 data demonstrates organisational improvement but not yet a step-change in renewable energy consenting times. The critical test will be whether RED III, the Planning and Development Act 2024, additional staffing and improved case management translate into faster and more predictable decisions during 2026 and beyond.

Read the full report